Hi expert,
I have question with BOM and production process. In packaging industry, At start we have 8 components for finish goods. but recently, 2 component 0020 and 0030 (example bottle cap and sticker) will issue from warehouse for assembly process before return to warehouse. then re-issue to use for finish goods.
usually component 0020 and 0030 will convert to another component or change to semi-finish goods.i must create this BOM , Routing , and Open Production Order.and change component in finish goods,
if i not create BOM , Routing , and open Production Order. but create new component as semi-finish goods for item from assembly process to use in finish goods BOM as phantom assembly.
how is my resolution, possible or impossible? , will be any problem in the future. any advise is good.
regards,
kittisak.