12-09-2008 2:06 AM
hi guys,
how do i download variant from a report in qas and upload it to the same report in production?
12-09-2008 2:27 AM
12-09-2008 2:30 AM
Thanks Amit, is there a way to do it the other way around, from production to qas?
12-09-2008 2:37 AM
Execute RSVARIVALCLI from Se38 for copying variant between client.
12-09-2008 2:56 AM
hi Amit,
Our client between dev, qas and prd are the same , it is called client 100, so i can't use RSVARIVALCLI , pls advice..thanks
12-09-2008 3:02 AM
One more option you may try is, Just create request Form RSTRANSP and than from t-code SCC1 Move transport request.
But I would suggest you to just create The Request in PRD and leave rest work for Basis person as you want to move in reverse way(PRD to QAT),so they will be able to do this job.
Just give them transport request and let them know to moe this to QAT.
12-09-2008 2:36 AM
hi,
yes , basis consultants can reimport the request from production to devlopment and quality.
also,you can get request from E070 and E071 tables.
thanks.
04-01-2009 4:51 AM