Hi MRP gurus,

Just looking at the s/4hana 1709 app "monitor material coverage". I found the settings for setting up the profiles for it in spro > production > mrp > apps for mrp > general settings... I was able to increase the evaluation period there to 365 days for the "MRP standard" Material shortage definition.

But the app itself still only gives me the option to set the Stock availbility chart to "Days" and "Weeks", not "Months" at all. Also I can't increase the number of days or weeks I want to look ahead...

I only can look at 7/14/21/28/35/42 days or 13/26 weeks.

I really want to look at 12months and 52weeks as well.

Is there a way to achieve that??

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 21 at 12:34 PM

    It seems you would have to do a bespoke/extend the app to show months or longer periods. The ABAP structures do not support more than 42 days and 26 weeks when you look at it in the backend...

    See SAP Note 2249684 - MRP Apps: Weekly Availability chart attribute in oData

    Add comment