cancel
Showing results for 
Search instead for 
Did you mean: 

Monitor Material Coverage - Fiori app - Stock availability settings

BjornHarzer
Participant
0 Kudos

Hi MRP gurus,

Just looking at the s/4hana 1709 app "monitor material coverage". I found the settings for setting up the profiles for it in spro > production > mrp > apps for mrp > general settings... I was able to increase the evaluation period there to 365 days for the "MRP standard" Material shortage definition.

But the app itself still only gives me the option to set the Stock availbility chart to "Days" and "Weeks", not "Months" at all. Also I can't increase the number of days or weeks I want to look ahead...

I only can look at 7/14/21/28/35/42 days or 13/26 weeks.

I really want to look at 12months and 52weeks as well.

Is there a way to achieve that??

Accepted Solutions (0)

Answers (1)

Answers (1)

BjornHarzer
Participant
0 Kudos

It seems you would have to do a bespoke/extend the app to show months or longer periods. The ABAP structures do not support more than 42 days and 26 weeks when you look at it in the backend...

See SAP Note 2249684 - MRP Apps: Weekly Availability chart attribute in oData