Dear Gurus,
My prodn order qty is 100.In Co11n or in Co12 i am confirming 90 as yield and 10 as scrap.What is the impact in terms of costing and goods movement.My scenario is a press machine sequence.If 10 pcs are damged during press.the 10pcs will become a scrap material which i will sell to the the different customer in kgs.
say 1 fg cost 100rs
say 1 rm cost 10 rs.
operation 10: press1 : yield 90:scrap:10
operation 20: press1 : yield 90:
operation 30: press1 : yield 90:
operation 40: press1 : yield 90:
Please through some light on this issue.
Regards,
Guna
TCS