Dear Gurus,

When I am confirming the production order, Labour time gets confiremd for the order quantity and not for the yield quantity. Means eg.

Say order qty is 100 and time required for processing a particular operation is 5 minutes.

So when I am confirming the partial quantity 10 labour time confirmed is 500 instade of 50. The for nex partial confirmation again 500.

Can you give solution on this please.

Regards,

RG