on 12-06-2008 7:06 PM
hi ,
During confirmation of operation at co11n (also at co11), got one error massage i.e "actual activity allocation is not allowed for order "
Due to this error confirmation is not possible .
pls help me to solve this problem.
AMOL WAGH
Edited by: amol wagh on Dec 6, 2008 8:09 PM
Edited by: amol wagh on Dec 6, 2008 8:10 PM
Dear friend,
can u please post message no.?
sree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
For allocation activity costs, we need to define activity type in KL01 by specifying the unit of measurement of the particular activity type (like machine - Hours etc.). While creating activity type, we will assign a secondary cost element (with category 43) in the activity type through which the activity cost will flow.
After that we will plan for cost center in KP06 (cost elementwise). Then we will plan machine hours in KP26 where we will link the activity type to a particular cost center.
Please give the feed back.
Regards,
R.Brahmankar