Hello.
We want to use the Assembly Scrap field in the Material Master, to increase the quantity of the assembly planned orders by a certain percent, and in consequence every component in it.
However, we don't want to have that Assembly scrap percent be reflected in the Costing of the Assembly. Normally after I enter assembly scrap, when I cost the product in CK11N, it increases the Quantity of the components by that percent.
We want to avoid that, we just want to use the assembly scrap for Production, but we don't want to increase the standard cost of the assembly.
Is it possible? I'm looking at the Cost Component Structure for any possibilities, but I'm not finding anything.
Any help? Thanks!