Please find the scenario.. We have two plants, one is manufacturing plant and other is CKD plant. Based on the Stock transfer order generated at CKD plant, materials are stock transferred from manufacturing plant to CKD plant. In order to differentiate CKD requirements at manufacturing plant, we have created a separate MRP area (storage location MRP area. Here it is KD10) in the manufacturing plant. Stock transfer orders are always generated with issue storage location KD10 at CKD plant. MRP senses this issue storage location and creating planned orders for the MRP area in manufacturing plant. Till here the process is smooth and there is no issues.

Problem starts here for the dependent requirements of the planned order. We want some of the child items to be planned under same MRP area KD10. But currently, all the child parts are always planned under "Plant" MRP Area. For eg., CABT is the main stock transfer material. CABP, ZABC, ZXYZ are sub assemblies under CABT and subassembly CAB00 falls under CABP. Out of these, we need to plan CABP and CAB00 under the same MRP area KD10, if the requirement for CABT is from KD10.

Please let me know, what setting should I carry out to achieve this.