How to do material Stagging

241 Views

Dear Frndz,

I am doing the material stagging process by MF60.But, the system is not generating any procurement proposals.Kindly help me out in this issue, the following is the scenario.

For item FGA, I need two raw materials as RMA and RMB.The actual storage locn of RMA and RMB is 2111.The production storage locn of both the items are entered as 2112 in MRP-2 view in Prod storage locn field and storage locn of EP.

Now am creating a production order for FGA, then I go to MF60 and enter required details like Plant,selection period reqmts, order number and also am entering the global settings like Create Repln prop as "Automatic" and stage Repln proposal as "Automatic".Still the system is not creating any replenishmnt proposals.The system throws a message like"No reqmts determined according to the selected conditions".....Pls help me.

Regards,

Srini