Hey gurus,

I ve created a counter based plan and determined the counter value for which the maintenance plan should be called. Now every time i overflow this value i ve to go to the scheduling and save it then only the order gets released. How to automaticaaly trigger the order based on the counter reading without going to the schedule and saving it every time?

Regards,

Abhishek

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2008 at 06:43 AM

    Try using T.CODE IP30. Enter no. of days in future for which you want to do the scheduling and execute.

    SM

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear Abhishek

      For Counted based plan the planned date is dependent on annual estimate & counter reading you enter frequently. Suppose annual estimated is 1500 KM for bike that means bike runs 4.1 hous for a day. if you post reading 8 hours onec it will shift you planned date early by one day.

      if you want to do fixed date maintenance, better you for time based maintenance plan.

      Regards

      Makarand Gurjar

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2008 at 06:44 AM

    Hii

    PLease take run for deadline monitoring program for all plans. Please use IP30 transaction for this.

    I think this will resolve your problem.

    Regards

    Makarand Gurjar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 05, 2008 at 06:49 AM

    hi

    you can also use IMRC0001,but it has some restriction likeIt makes sense to use this customer exit if you have a large number of maintenance plans, but only a few measurement and counter readings.

    regards

    thyagarajan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 08, 2008 at 11:43 AM

    Hi Abhishek,

    You need not overflow the counter to achieve a call. An overflow is a condition where a counter exceeds the max value CntrOverReadg defined in the counter. After it exceeds or overflows , the counter is reset to its initial count.

    Example

    Last displayable counter reading 999

    Last counter reading 990

    Units used 20

    New counter reading after counter overflow 010

    You just need to schedule the plan using deadline monitoring IP30 (provide interval for call objects, tick rescheduling inclusive, tick immediate start for all.)

    Then u have to fill the counter reading in the measurement document. When the counter reading corresponds to the call date, it will automatically generate a call.

    Saurabh.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.