Skip to Content
0
Former Member
Dec 05, 2008 at 05:48 AM

Day's Supply

28 Views

Hi All,

I have one query on day's supply calculations.

Suppose stock as on date( 05-12-08) for a material is 1

1st Requirement which is on (09-12-08) for the material is 4

Then what should be the day's supply.

As per the help 'The range of coverage is then the number of workdays between todays date and the date of the requirement that causes the shortage minus one day. The value after the decimal point is the ratio between the opening stock on the day of the shortage and the requirement on the day of the shortage'. According to it the day's supply should be 4-1+(1/4) = 3.25

But actually system is displying the value of 0.25