on 12-05-2008 4:51 AM
Hi Gurus,
I have created a planning Scenario - 999, for plant 1000.
In OPU5, i have entered the scenario.
Created a reqirement in MD61 with version 01(in active).
In MS32, in the Planned Independent requirement tab,I have entered "01" in the versionfield & "00" in the target version field. (IAM NOT SURE WEATHER IAM RIGHT HERE, PL. CORRECT ME IF IAM WRONG).
Created planning file entries.
executed MS02
checked MS04.
I could not see any required capacity in CM38
Am i failing somewhere? pl. help.
regards,
K.Kumar.
Dear Kumaran,
1.A plannig scenario has to be created for a plant in T code MS31 & for the same Planning scenario
configuration settings has to be made in OPU5 for the planned orders for LTP.
2.Requirements has to be given in MD61 in an inactive version and also after giving the requirements
kindly remove the tick mark against version- active check box.
3.Assign this plan to the planning scenario in MS32,release it and ensure the planning file entries are
entered or created,the same can be checked using MS21.
4.After taking LTP simulation run in MS02(individual material) or MS01 you can see the simulated
planned orders obtained in MS04 T code.
5.These Simulated planned orders can't be converted into production orders or it cant be used for any
business confirmation purpose.
6. For capacity planning analysis,use T Code CM38,
Before that Ensure for all the work centers in CR03 which are used for operation under capacity header
you have included the check box for Long term planning,otherwise in CM38 you can't see any capacity
requirements data.
7.Before executing CM38,ensure under settings---> general you are giving the period settings properly.
Revert back incase of any more clarifications required.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kumaran,
This only a guess,since I have not used that option so far,When you want to activate that inactive
version requirements you can mention the source version (in active version) and the target version say
00 (To active version) .again there's test mode to check the execution and a create List mode.
Also check T Code MS64, to copy the requirements data from one version to another version.
So is your previous issue solved?
Revert back still if you have any queries.
Regards
Mangalraj.S
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi mangal
in the first place i would be happy to know from you what is the purpose of LTP when all other methods are there..i need to explain to my client coz as of nw he is using MRP alone..he asks for SOP and LTP
for REM purpose
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In LTP run MS02 screen, please ensure scheduling key is 2 (Lead Time scheduling).
Thanks,
JK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
RUN MRP with lead time scheduling.
In work center capacity tab work center should mark for finite scheduling and Log term planning.
In CM38 and check the evaluation period and selection profile?
Check result in CM01 for capacity generation?
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.