"revert the posting period"

Hi,

Using T-code MMPV one of our consultant has opened posting periods upto Febraury month ( using V3 as fiscal variant) also can we take that posting period back . can any one tell me the procedure how to take the period back for 2 months.

Regards,

Deva

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Best Answer
    Dec 04, 2008 at 11:56 AM

    Dear Friend,

    If you are using period starting from April 2008, then correct Posting Period for December 2008 is 09/2008.

    But if seems in your case some has by mistake opened 11/2008. That means 09/2008 is closed & you cannot to material movement entries in a closed period.

    You can open closed MM periods, but be really careful next because even SAP does recommend opening closed MM periods.

    Anywasy follow this:

    T-Code: MMPI - from Tool Bar select - System - User Profile - Own Data - In parameter Tab Enter "MMPI_READ_NOTE" in parameter Field

    Then, Remove assignment of Plants from Company Code (In SPRO).

    Now use T-Code OMSY & Set the required Period.

    Re-assign Plants to Company Code & Check whether correct preriod is open thru T-Code - MMRV

    Now use T-code - OMWD to Assign Valuation grouping code to Valuation area because the earlier data gets deleted when assignment of Plants was removed.

    Use the transaction code OMS2 then select FERT (or any other Material Type used by your company)

    Then click on the quantity and value update.

    Select your plant or valuation area and put Tick Marks in Value update and Quantity update

    This will definitely reslove your problem

    Give points if useful & close the thread...

    Thanks,

    Jignesh Mehta

    Mumbai

    98700 10230

    Edited by: Jignesh Mehta on Dec 4, 2008 5:28 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 04, 2008 at 11:24 AM

    Hi

    As of my knowledge you can't revert the MM posting periods. However you may post this message in MM forum. Only FI posting periods can be adjusted.

    Regards

    Murali

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 04, 2008 at 11:27 AM

    Hello,

    Do not try anything now. Contact your FI expert , he will help you.

    Prase

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 04, 2008 at 11:31 AM

    Hi,

    Pls check following link. It may be useful to you

    MB1C

    Regards,

    Abhee.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 04, 2008 at 11:38 AM

    Dear Devaselvam,

    Had you tried with T. Code: OMSY (for Variants, V3 and K4)