Hi Experts,

In my project Basis people are going to down the BW production server, in this project total 37 process chains are there, in this time what kind of action i have to take on process chains, .

Please guide me......

Thanks in advance

Venkat

Accepted Solutions (1)

Accepted Solutions (1)

nvytla
Participant
0 Kudos

1. Check if any process chains are going to start and still run during the down time.

If so, stop them and schedule them after... so that no process will end in the middle....

2. If there are some process chains scheduled to start during the down time.

If possible run them in advance or you can schedule them after words since this schedule will be skipped.

Hope it helps,

Naveen Vytla

Answers (2)

Answers (2)

Former Member
0 Kudos

my question was answered

0 Kudos

Hello,

I don't think there should be any problem due to this basis work.

Just once server is up, you have to reschedule the process chains which are missed out in that server down time.

Thanks,