We have created a project in PS.
While generating Purchase Requisition thru MRP in MD51, account assignment category (Q) is coming, but the account assignment tab is missing in the purchase requisition.
But when we are generating PR thru CJ20N with prelimnary requirement as a procurement indicator then the WBS is getting fetched in Account assignment tab.
Please assist urgently,
Thanks
Sanjay