on 12-03-2008 1:41 PM
Hi experts,
In our project, For many int. activities we require 3 different skill level labors, say Skilled, Semi-skilled and Helpers to perform the activity and the cost of these labors are different. Whereas, in int.activity tab, we can assign only one activity type for a work center and thus cost for only one type of labor. What should be done to capture costs for all these labors in single activity?
use the functionality of activity element to assign more than one work centres to your activity
under the activity attach 2 more activity elements with different work centres and activity types
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |