Skip to Content
0
Former Member
Dec 03, 2008 at 12:34 PM

CJI4 Report do not shows any values

1350 Views

Hi Experts,

I plan my project costs by Network Costing.Mostly i have service activities.When I post the actuals,I am able to analyse the actuals in the Line Item report CJI3.

In the same way i want to analyse my Plan cost line items,But my CJI4,Plan cost line items report show no values,Though my period,Fiscal year entered are correct,Plz provide inputs on what could be the reason.