on 12-03-2008 4:45 AM
Dear Friends,
How to handle Material Availability checks in Repetitive Manufacturing
If Missing Parts is there no Backflushing is allowed.
Regards,
Jimmy
Dear SDN Creature,
In the REM Profile in T Code OSP2 - under control data 1 include the check box for Execute correction
in dialog mode and select the radio button for Mandatory.
If you are assgning this REM profile to the FERT or HALB materials while doing the backflush if there is
any deficit of components,then the syetm will now allow to do the confirmation.
There's no other check for missing parts in REM.
So check with this & revert back if there is any queries.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
I'm not sure but pls try this maintained stock determination rule and stock determination group and assign to the remin config. and maintained stock determination group in material master
For details refer this SAP help.
http://help.sap.com/saphelp_46c/helpdata/en/8a/a5aab64adc11d189740000e8322d00/frameset.htm
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.