Role - Resource - Task Assignment

36 Views

All,

We have a requirement where a cProjects task may spread along for, say, 6 months. Resource needs to work on this task for only 2 days per month, every month (say) (Work - 12 days).

When the role is staffed for 6 months, this resource will not be available for the other projects. And therefore, we want the resource assignment to the task to drive his availability.

Is there a way out? Or do we have to staff the role 6 times (with the right dates)? The second option works, I know, but is not an elegant way to do it.

Thoughts/opinions.

Regards.