Hi Gurus,
Actually i am facing a problematic situation. I m on client side. currently they are manufacturing against sales order. But many times what happens they starts the production only on customer mail without sales order. they received the purchase order in between when the production completed 60-80 %. In this situation which strategy should be use and how to map this process in sap. Pl. suggest me any one proper method to deal with this situation.
Thanks in advance
Regards
Ravinder Kumar
Hello
Strategy 20 is the pure MTO, where the products are assigned to the sales order special stock. Since you don't have a sales order when you start the production, this strategy would not be recommended.
I suggest you to use strategy 40, where MRP reacts to sales orders and there is no assignment to the sales order stock. You create PIRs if you want, but this is not mandatory.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Create CIR (MD81) once you receive mail, start production against CIR, later on when you receive purchase order then create sales order & transfer stock from CIR to sales order (MvT 413-E).
Regards,
Mukesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.