Hello Experts,
I have a business case where my customer builds very large constructions. The have large BOMs (many levels) representing these constructions.
Obviously, they do not want to just assign the top material of this mulitlevel BOM to an activity and run MRP. they need to be able to assign different sub-components to different network activities to be able to track both costs and progression.
My problem is that I am not able to control how much of the BOM that explodes. The top assembly should be assigned to one activity, but there, I only want the BOM to explode down to the next level and so on.
I am sure that this is a quite normal requirement, but I am simply not able to solve it. Have spent hours on help.sap.com, talking to other consultants and looking in this forum without finding the answer.
All my components need to be held in stock, so phantom items will not help me.
Anyone who has any suggestions on how to do this?
rgds
GAR