Hi Experts,

Please give me complete cycle details with steps for Process orders.

from order creation to order settlement.

Regards,

Vivek

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 02, 2008 at 09:58 AM

    Hi,

    Please refer to link below:

    http://help.sap.com/erp2005_ehp_03/helpdata/EN/05/603bc6462311d182b50000e829fbfe/frameset.htm

    Process order creation

    Selecting a master recipe

    Creating reservations or copying them from planned orders

    Calculating planned costs

    Creating capacity requirements for the resources

    Scheduling

    Starting with the basic order dates, the system automatically schedules the process order when you create it. In addition, it can later be rescheduled automatically or manually whenever changes relevant to scheduling have been made.

    Release of process order

    Process order execution and process management

    Creating and downloading control recipes (optional)

    Printing shop floor documents

    Carrying out material withdrawals

    Withdrawing material components required in the manufacturing process in the form of goods issues from the warehouse.

    Recording confirmations

    Carrying out in-process quality inspections (optional)

    Posting goods receipts

    Delivering the manufactured product to the warehouse by posting a goods receipt.

    Thanks,

    Samuel

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      thanks Samuel,

      Please help me in this regards too.

      I have completed the goods reciept step for a process order.

      Now I am trying to do the following steps for the order settlement.

      1.Calculate Overheads using Tcode : KGI2 - Individual Processing

      CO43 - Collective Processing

      2.Calculate WIP using Tcode : KKAX - Individual Processing

      KKAO - Collective Processing

      3.Calculate Variance by using Tcode : KKS2 - Individual Processing

      KKS1 - Collective Processing

      4.Finally do the settlement of Order in Tcode : KO88 - Individual Processing

      CO88 - Collective Processing

      I am not able to do these steps.

      KGI2: the screen is appearing without any details,but there is no error message.

      KKS2: Here all the cost are coming zero.

      KO88: I am getting this message: There are no accrued amounts; settlement is not possible.

      Please advice.

      Regards,

      Vivek

  • Posted on Dec 02, 2008 at 10:08 AM

    Dear,

    Please check this link,

    [Process order steps|process-manufacturing-steps]

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 04:07 AM

    Thanks Brhamakar for your invaluable inputs.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.