Hi,
I have created material with safety stock (500 units ) and maintained monthly lot size . Then i given demand in md61 for same material of 1000 units . Now when i go for mrp run it is generating a single planned order , it is adding the the safety stock and PIR units and generating cummulative single planned order . my requirement is i want to generate a separate planned order for safety stock and PIR.
pl suggest
regards
sasikanth