Dear All,
I am configuring MRP for my client. The scenario is as below -
I have one Warehouse [ Plant A ] from where the demand for the Finished Good is generated. There are two Production plants [ Plant B and Plant C ] connected to the Warehouse A. Warehouse A is not able to produce any FG.
We have configured Plant A such that whenever MRP is executed in Plant A, it will generate a STO against Plant B by using Special Procurement Key.
The customer wants that while we execute MRP in Plant A, it should distribute the demand between Plant B and Plant C in a pre-defined ratio.
We tried Quota arrangement for this the way we generally do it for Vendor Distribution but was not successful.
Please suggest if there is a solution for the same.
Regards,
Kumar