Skip to Content
avatar image
Former Member

Can I distribute my MRP Production Quantity between two mother manufacturing plant

Dear All,

I am configuring MRP for my client. The scenario is as below -

I have one Warehouse [ Plant A ] from where the demand for the Finished Good is generated. There are two Production plants [ Plant B and Plant C ] connected to the Warehouse A. Warehouse A is not able to produce any FG.

We have configured Plant A such that whenever MRP is executed in Plant A, it will generate a STO against Plant B by using Special Procurement Key.

The customer wants that while we execute MRP in Plant A, it should distribute the demand between Plant B and Plant C in a pre-defined ratio.

We tried Quota arrangement for this the way we generally do it for Vendor Distribution but was not successful.

Please suggest if there is a solution for the same.

Regards,

Kumar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • May 22 at 09:10 AM

    While using Quota arrangement did you allow splitting of quota for the lot size that you have used?

    Regards

    Raghavendra

    Add comment
    10|10000 characters needed characters exceeded

  • May 23 at 10:40 AM
    Add comment
    10|10000 characters needed characters exceeded

  • May 24 at 07:25 AM
    Add comment
    10|10000 characters needed characters exceeded