Dear all,

I am wondering why the available capacity for a work center remains the same in CM02 even after reducing the operating time.

Operating time = (Working time - Break time) x Capacity utilization rate/100%

https://archive.sap.com/discussions/thread/3263305

I have reduced to 2 H of operating time per day for my test, but no change in CM02 as a total available capacity.

Do I have to reinitialize the capacity of the work center?

Thanks in advance