Hi Experts:

We are doing the cost estimate yearly. In the mid year, as the FX rate is changed so we want to re- calculate the standard cost. One problem with this is that in order to be able to change cost estimates mid year we would need to delete the existing estimates. The way we do that now is by using CKR1 which requires all open sales orders, process orders for those materials to be closed which if we would do a re-costing for a company code would be nearly impossible.

Can you advice if there is any other way of doing this?