Hello,
We want to use time phased planning with MRP, so that we plan the material every Tuesday to be delivered on Friday.
We created a Z MRP type copy of standard time phase plannning type and selected the MRP requirements.
Next, we maintain the planning cycle as Tuesday and Plannning calendar as Friday (Delivery Cycle) on the material master record.
Issue is, when we run MRP on Sunday, the materials is being planned and system is creating the PR's even though the planning cycle shows that the material should be planned on Tuesday only and we checked the Planning file entry and it shows Tuesday as well, not sure why system is planning this material on Sunday MRP run, can you please advice what we are missing.
Thank you very much..