Dear Gurus,

I am using CO11N for confirmation.

When i give confirmation / order number in initial screen and click on actual data system is proposing quantity to confirm. But it is not proposing activity to confirm.

I have maintained

immediate proposal for quantity/services in OPKI for time ticket.

Propose quantity / propose services for plant/order type in OPK4.

Immediate proposal for quantity/services in OPK0.

After confirmation when I go to CO14 and check confirmation under quantity/activity tab,

In case of quantity, i can see total planned quantity and already confirmed quantity. This is OK.

For activity, I can see confirmed activity, but planned activity is 0.00 min.

what can be the reason? How can I display planned set up and machine time?

Regards,

Himanshu