Dear Gurus,
I am using CO11N for confirmation.
When i give confirmation / order number in initial screen and click on actual data system is proposing quantity to confirm. But it is not proposing activity to confirm.
I have maintained
immediate proposal for quantity/services in OPKI for time ticket.
Propose quantity / propose services for plant/order type in OPK4.
Immediate proposal for quantity/services in OPK0.
After confirmation when I go to CO14 and check confirmation under quantity/activity tab,
In case of quantity, i can see total planned quantity and already confirmed quantity. This is OK.
For activity, I can see confirmed activity, but planned activity is 0.00 min.
what can be the reason? How can I display planned set up and machine time?
Regards,
Himanshu