I was trying to release a cost estimate with an effective date of 12/01/2008 and received the error message CK157 - Release too Early. "The start of period 012 is 12/01/2008, which has not been reached."
Here is my dilemma - The release was for our China company which is 12 hours ahead of the US. The SAP 'system time" is US.
I checked the current period for our China location and the MMPV program was ran and the current period was 12. I also checked the OB52 and the posting period 12/2008 was open.
The only note that I could find was 657454 - Release: Message CK 157 unjustified. This sounds like the problem but this note is already installed in our system. This note was part of SAPKH47016 and we our on support pack SAPKH47028.
Any help would be greatly appreciated.
Regards,
Greg