Hi,
We have set up a small PI scenario. The issue we are facing is that the target costs are not displayed in the order. Actual costs appear after confirmation, but target costs appear as zero.
We have maintianed cost relevancy in work centers, defined valid activity types, maintianed price in material master for all components and also run the standard cost estimate and released it.
Please let us know what we are missing and why this error could be happening?
Thanks in advance,
Ashok