Hi,
i have one query,my client has 4 plant,for manufacturing a product there are 10 operation.The 4 operation is taking on Plant A.The 5th and 5th operation is is in Plant B.The 7th operation is at Sub-contractor to vendor and return back to Plant A,and the remining operation is at Plant A.
So what are the Master Data and MRP we have mainted for that?
Please revert back.