round total value after cost estimate with ck11n?

315 Views

Hi Experts,

in advance thanks a lot for useful previous answers ,

I have a problem when creat cost estimate for material,

when i cost estimate material with T.Code:CK11N ,total value for each item is rounded with this alghoritm:

(IRR is our currency)

Value<25 IRR.................................. total value=0

25<=Value<75 IRR...........................total value=50

75<=Value<125 IRR..........................total value=100

125<Value<175 IRR.........................total value=150

i think it's better to get some information about how calculate value:

after price calculation for costcenter/activity type ,operation that done in routing is multiplied with activity rate and after that value is rounded.

activity rate:833 irr/min

operation tme: 0.05 min

for exam: 0.05 min * 833 irr/min = 41------>total value=50 IRR

my question is that are there any setting in customization for total value in cost estimate or not?

Can anyone shed some light on this.

Your help would be appreciated.

Thanks.

Azam