Greeting ..
i have cerated on e work center with all its view.
Now Create one routing , and assigned this work center for one of its opeartion and saved the routing .
If see the routing in change view ....and double click on work center.....in scheduling view i m not getting any data in that scehduling view of work center,
I see change view of that work center then i m getting scheduling data.
BUt not copoied to routing.....due to this in produciton order that opeartion is not schdeuling.
pelase suggest....