Former Member
Nov 29, 2008 at 01:27 AM

Internal Manufactured Requirements

18 Views

Dear All,

Our client is in Metal Industry. All his orders are projectized inside PS, they have deliverables which for example is Material X. This material X is consisted of materials A B and C. Once A/B/C are manufactured X just be complete.

I tried used Strategy Group 21 (Make to Order / Project Settlement) and Special Procurement 52 (Collective Order) and placed a requirement inside the project system for Material X.

once I run MRP, it generated Ordersfor X/A/B/C. My problem is, after I finished any of A/B/C I want to deliver them to the project stock and have X complete. Special procurement 52 doesn't allow me to do any deliveries (GR) for A/B/C, only for X.

What's the best practise for this?

I was thinking of making a project WBS bom for material X and putting in it A/B/C but I don't know what impact this WBS BOM will do.

Please understand that in the project system the team only asks for X, they dont know that it is made from A/B/C until the technical department lists these structures (after looking at technical drawings)