Skip to Content
0
Former Member
Nov 28, 2008 at 05:52 PM

PO acknowledgement

72 Views

Hello,

I don't understand the difference between the acknowledgement flag and the confirmation control key in the PO.

1) what happens if I just flag that a confirmation is required but I don't select confirmation control key 0001?

2) if I select confirmation control key 0001 and AB and I enter the dates and quantities, what is then the difference between the dates and qty in confirmation tab and the deleivery schedule dates and quantities? there is no synchronization between those 2 tabs. what does MRP look at?

Sofia