hello ,

The Purchase Order was printed straight away without going through Release Strategy.

Release Strategy is not RE-ASSIGNED again even though PO value has been changed.

When we changed the Overall Limit of the Item to very significant amount then only release strategy got RE-ASSIGNED to Purchase Order.

Calculation of Net Order Value

Initial Net Value - 1872227.02

Changed Net value - 3545962.73

The Difference in the Net value u2013 1673735.71

So when the Net value changed to 3545962.73 then Release strategy got Re-Assigned again to the PO.

Edited by: Matt on Nov 28, 2008 8:26 PM