Skip to Content
0
Former Member
Nov 28, 2008 at 03:07 PM

ATP / MRP stor loc exclusion

21 Views

My problem occurs at Work order creation, OPJJ setting (scope of ATP check) is set for "Not looking at storage location" for all component.

Ex:

Requirement component A = 100 in SLOC 30

In SLOC 30 availability = 30

In SLOC 10 availability = 70

Therefore, cosidering the OPJJ setting I should have 100 confirmed. (no storage location check)

BUT

If the MRP exclusion (MARD-DISKZ = 1) is set for SLOC 30, the confirmed quantity is 30.

If there's no MRP exclusion (MARD-DISKZ = Blank) on SLOC 10 and 30, the confirmed qty is 100...

This seems to be standard SAP functionnality. Is there known workaround?

I tried user exit ATP00001 not a success...

Thanks