Hi Experts,
How can we distribute the cost planned in service activity equally through out the scheduled period?
Like in internal activities, the cost will get distributed in all the periods proportionately in which it is scheduled.
As of now in CNS41 if we go to the period breakdown of the order cost plan of the service activity, the cost plan is displayed against the last period of the service activity only.But my client says the subcontractor can raise a bill after completing every month work.In that case my order cost plan will show zero in the first period,if the service activity is spread across two months.But for that we cannot divide a single service activity which is spread across 2 months into two activities.
Plz suggest some solutions.....How to set up equal distribution key for service activities costed thru Network costing...