cancel
Showing results for 
Search instead for 
Did you mean: 

Priority 5 is not supported: Solution Manager Work Centre Setup

Former Member
0 Kudos

Hi All

We are currently getting this issue in our Solution Manager Work Centre setup. We are usingf SOlution Manager 7 SP 16. The full alert / message is:

Not all priorities are in customizing or supported - Priority 5 is not supported

I have gone throught SAP Note: 964598 and we still get this message appearing. I have checked the table SCPRIO and this Priority 5 does not exist. However when I try and check SCPRIOT i get a message:

The maintenance dialog for SCPRIOT is incomplete or not defined

Has anyone had this issue and know how to fix this problem, please help!!

Thanks for your time

Phil

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Sol Man 7.0 SP16 - I got following entries:

SCPRIO

CLIENT PRIORITY TXT_LONG

100 1 1: Very High

100 2 2: High

100 3 3: Medium

100 4 4: Low

100 5 Medium

100 9 Low

SCPRIOT

CLIENT PRIORITY LANGU TXT_LONG

100 1 D 1: sehr hoch

100 1 E 1: Very High

100 2 D 2: hoch

100 2 E 2: High

100 3 D 3: mittel

100 3 E 3: Medium

100 4 D 4: niedrig

100 4 E 4: Low

100 5 D mittel

100 5 E Medium

100 9 D niedrig

100 9 E Low

I am not sure but I don't think I ever created entries manually in these tables.

Regards

markus_doehr2
Active Contributor
0 Kudos

> I am not sure but I don't think I ever created entries manually in these tables.

Those priorities come with BASIS support packages. We have some of them 4 times, others 3 times...

Markus