Skip to Content
0
Former Member
Nov 27, 2008 at 01:59 PM

KKS2 -Variance Calculation Issue

21 Views

Hi,

i have executed Variance calculation in KKS2 transaction code.After execution of this,i am getting one list.In that list it is giving one amount under Target Costs.This target amount differs from Actual Costs & Actual Costs Allocated.

what is this Target cost? why we are getting this? from where we get this value?

Kindly advice me.

Thanks

Sunitha