Nov 27, 2008 at 12:31 PM

Milestone billling

31 Views

I am using the Milestone Billing Manual entries, where i am manually changing the Item cateogry for the material for Billing Plan in the order .

I have a order of 1,00,000 Rs for line item . i am using the milestone billing for this line item where billing is done on % basis.

like 30 % , first stage of project

next 50 % second stage of project

final 20 % of the project

When i am doing the billing for the first stage 30 % that is 30,000, using the F1 as this is order -rel- Billing, the system is picking up the total value of the Invoice that is 1,00,000.

plz guide me