on 11-27-2008 7:32 AM
hi
i want to plan variable cost, please advise t-code
bcoz in kp06 only fixed cost can be plan.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
no body answer is correct
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thkx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Imdad,
You can maintain the variable costs in KP06.
You have to select the proper layout for that. Select the layout 1-104 i.e Primary/Secondary Order Costs.
I hope your Standard layout in KP06 screen is 1-101 i.e Cost Elements Acty-Indep./Acty-Dependent
Hope this will resolve your problem
Regards,
Makrand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
You have to maintain it in KP26
In KP26, when entering the cost of activity, system provides an option to enter costs separately.
for varaible cost.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think you can do it in KP06.
Regads
Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.