Need your help,
scheduled process order which have one operation say 100 and three phases 110,120,130.
Phase 110 starts at 10/22/08 , 13:56:50 and end at 10/22/08 14:28;25
Phase 120 starts at 10/22/08 14:28;25 and end at 10/22/08 24:00:00
Phase 130 starts at 10/24/08 23:20: and end at 10/24/08 10/25/08 02:30:00
For Phase 130 Ealiest start date is 10/23/08 00:00:00 Latest start date is 10/24/08 23:20:32
Ealiest finish date is 10/23/08 09:09:28 Latest finish date is 10/25/08 02:30:00
What could be the reason for diff in ealiest start & latest start,ealest finish & latest finish date .
Note 10/23/08 is a working day in factory calender .why order is not scheduled on 10/23/08.