"Selected unit is not suitable for dimension of resource" error for resource in apo

While setting non working day under time capacity for a resource , we are receiving an error "Selected unit is not suitable for dimension of resource". This is happening after a recent upgrade.The unit capacity is maintained as 'H'.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Nov 04, 2016 at 07:11 PM

    Hi Satyabrata,

    Please, make sure attached note below is implemented:

    1962164 - Missing days in time stream / Capacity profile / Dump CONVT_OVERFLOW

    Afterwards, regenerate the capacity profile and make sure that the first entry / day is not a non-working time.

    Regards,
    Tiago