"Selected unit is not suitable for dimension of resource" error for resource in apo

Nov 04, 2016 at 02:35 PM

28

avatar image

While setting non working day under time capacity for a resource , we are receiving an error "Selected unit is not suitable for dimension of resource". This is happening after a recent upgrade.The unit capacity is maintained as 'H'.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Tiago Furlanetto
Nov 04, 2016 at 07:11 PM
1

Hi Satyabrata,

Please, make sure attached note below is implemented:

1962164 - Missing days in time stream / Capacity profile / Dump CONVT_OVERFLOW

Afterwards, regenerate the capacity profile and make sure that the first entry / day is not a non-working time.

Regards,
Tiago