on 11-26-2008 7:03 AM
Hi All SAP PP Gurus,
When i'm executing order confirmation by using T/C- co15.I'm getting the problem
*_No price could be determined for internal activity LABOUR 0000005006_***
here 5006 is a cost center.
Thanks & regards.
Ganesh
Maintain Price in Tcode: KP26 for the activity type.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
If u want to maintain the activity price manually then use T-code KBK6 or else follow the kp26 process.
Regards
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
T Code KP26, maintain the fixed prize for the combination of the activity type and cost centre
Check plan cost for cost center and activity in KP06
It will solve your problem.
Regards,'
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Ganesh Kumar,
1.Create a Cost center using T code - KS01.
2.Create an activity type using T code - KL01.
3.Assign the Rates for an activity type & cost center combination using T code KP26.
4.In the input screen of T code KP26 ,enter version as 0, from period 1 and to period as 12 and the
Fiscal Year as 2008,enter the cost center, activity type click on overview screen (F5)---> enter the per
hour Rate under Fixed price and set value as 2 for distribution key and plan price indicator as 3.
5.After performing this ,while creating the work center ,this combination of activity type & cost center
should be assigned.Then while creating routing/task list this work center can assigned for performing
operations.
check with this & revert back.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check the labour activity in kp26,whether price has given or not.
after that u check the material whether cost has relesed or not
please come back if u have any queries on the same
Regards
Sukendar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.