No price could be determined for internal activity LABOUR 0000005006

Former Member
0 Kudos

Hi All SAP PP Gurus,

When i'm executing order confirmation by using T/C- co15.I'm getting the problem

*_No price could be determined for internal activity LABOUR 0000005006_***

here 5006 is a cost center.

Thanks & regards.

Ganesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Maintain Price in Tcode: KP26 for the activity type.

Answers (5)

Answers (5)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

hi,

If u want to maintain the activity price manually then use T-code KBK6 or else follow the kp26 process.

Regards

Ramesh

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

T Code KP26, maintain the fixed prize for the combination of the activity type and cost centre

Check plan cost for cost center and activity in KP06

It will solve your problem.

Regards,'

R.Brahmankar

former_member184655
Active Contributor
0 Kudos

Dear Ganesh Kumar,

1.Create a Cost center using T code - KS01.

2.Create an activity type using T code - KL01.

3.Assign the Rates for an activity type & cost center combination using T code KP26.

4.In the input screen of T code KP26 ,enter version as 0, from period 1 and to period as 12 and the

Fiscal Year as 2008,enter the cost center, activity type click on overview screen (F5)---> enter the per

hour Rate under Fixed price and set value as 2 for distribution key and plan price indicator as 3.

5.After performing this ,while creating the work center ,this combination of activity type & cost center

should be assigned.Then while creating routing/task list this work center can assigned for performing

operations.

check with this & revert back.

Regards

Mangalraj.S

Former Member
0 Kudos

Please check the labour activity in kp26,whether price has given or not.

after that u check the material whether cost has relesed or not

please come back if u have any queries on the same

Regards

Sukendar