No price could be determined for internal activity LABOUR 0000005006

Hi All SAP PP Gurus,

When i'm executing order confirmation by using T/C- co15.I'm getting the problem

*_No price could be determined for internal activity LABOUR 0000005006_***

here 5006 is a cost center.

Thanks & regards.

Ganesh

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 26, 2008 at 07:04 AM

    Maintain Price in Tcode: KP26 for the activity type.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 26, 2008 at 07:10 AM

    Please check the labour activity in kp26,whether price has given or not.

    after that u check the material whether cost has relesed or not

    please come back if u have any queries on the same

    Regards

    Sukendar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 26, 2008 at 07:14 AM

    Dear Ganesh Kumar,

    1.Create a Cost center using T code - KS01.

    2.Create an activity type using T code - KL01.

    3.Assign the Rates for an activity type & cost center combination using T code KP26.

    4.In the input screen of T code KP26 ,enter version as 0, from period 1 and to period as 12 and the

    Fiscal Year as 2008,enter the cost center, activity type click on overview screen (F5)---> enter the per

    hour Rate under Fixed price and set value as 2 for distribution key and plan price indicator as 3.

    5.After performing this ,while creating the work center ,this combination of activity type & cost center

    should be assigned.Then while creating routing/task list this work center can assigned for performing

    operations.

    check with this & revert back.

    Regards

    Mangalraj.S

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 26, 2008 at 07:14 AM

    Dear,

    T Code KP26, maintain the fixed prize for the combination of the activity type and cost centre

    Check plan cost for cost center and activity in KP06

    It will solve your problem.

    Regards,'

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 26, 2008 at 07:21 AM

    hi,

    If u want to maintain the activity price manually then use T-code KBK6 or else follow the kp26 process.

    Regards

    Ramesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Feb 15, 2010 at 04:37 AM

    thanks

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.