on 05-16-2018 10:06 PM
I was planning to use PPDS for S/4HANA to execute DRP. In order to do detailed scheduling of STR's and pegging it to MPS Planned Orders, I need to assign Transportation Resource in TLane. Intent is in DS Board, when i reschedule the pegged MPS Planned Order, the associate STR should also move along with it.
But since PPDS for S/4HANA doesn't allow to use Mixed resources, I'm not able to define the bucket capacity on S/4HANA Work Center (CR01/CR02)
Is there a work around or am I missing anything?
Appreciate your response.
Thanks,
Mangesh