How do you handle past-due Purchase Orders in IBP Optimizer?

274 Views

Hi Experts,

We are bringing in Purchase Orders/Stock Transfer Orders from S4 into IBP as "MINTRANSPORT" and thus they are incorporated as an input to the supply optimizer. How do you ensure that the purchase orders that are past-due are included in the supply plan? eg: If I have a Purchase order on a past date, that was partially fulfilled, how do I ensure that the supply optimizer considers the in-delivered quantity in the future runs?

Let me know if there is a standard way to handle this.

Regards