cancel
Showing results for 
Search instead for 
Did you mean: 

sd issue t-code lx47

Former Member
0 Kudos

hi

Here to t-code is LX47 which is ment for the delayed delivery date

and the problem is when i run the t-code i given the warehouse no and activate the

activate item

analyze TO item here also i activated but the result is not showing the error is "no data available "

so how to run the repotr and what r the prerequisite to run the report plz guide me ,

thanks inadvance ,

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

I think you have a wrong impression about LX47.

Have you read the docu behind the blue info button at the selection screen?

Former Member
0 Kudos

hi

Thanks for the response

here the user want me to immplement the t-code so that i am doing some test case but i stuck .

how to go ahead further i created two deliveries then i run the t-code lx47 here i entered the warehouse no and the delivery no from and to eventhough i get the error no data available .

so that can u help me how to test the t.code lx47 .

thanks inadvance.

Former Member
0 Kudos

hi

Thanks for the response

here the user want me to immplement the t-code so that i am doing some test case but i stuck .

how to go ahead further i created two deliveries then i run the t-code lx47 here i entered the warehouse no and the delivery no from and to eventhough i get the error no data available .

so that can u help me how to test the t.code lx47 .

thanks inadvance.

JL23
Active Contributor
0 Kudos

looks like you did not understand what SAP wrote.

One user is locking the delivery because he has the delivery open in change mode.

An other user confirms the related WM-transfer order.

In this case the status in the delivery is not updated.

To update this delivery status, you have to run LX47, and only then it will have a result.

Former Member
0 Kudos

hi

thnaks for your reply and you mean to say that this is a standard sap ,

but here they want to implement like that they are asking me

so what can i propose to them and explain to them this is the report standard report ,

orelse can u suggest me how can i convience to them plc help me out .

thanks v much .

JL23
Active Contributor
0 Kudos

I do not understand what your business requirement is.

Can you please explain?

Former Member
0 Kudos

hi

yeh i am explaing what they given me the task here under they asked me the explanation i given to them is the discription in the t.code now they want me to implement this is the situation.

"Please give me an explanation of what LX47 is used for and if it has

been set up within client to use - if not please set up.

Please implement as this woudl help us with out OTD

requirements - if we have access to it then it should be made available."

thanks inadvance.

JL23
Active Contributor
0 Kudos

Maybe somebody else can translate the sap help and what I wrote for you again.

Former Member
0 Kudos

Hi Jürgen L..

,

Thanks for the reply , here i wrote some description regarding this t.code lx47 ok,that may be , may not be the exact one by seeing this situation whatever u think and which will be the best one to convience them wrote me that will be v helpful for me.

thanks in advance,