Dear Expert,
I am maintaining cost center in process order as settlement rule(in Menu > Header > Settlement rule ) for 100 %
But in MB51 screen I am unable to find cost center name against consumption(261 movement type)
There is any setting required to visble cost center in MB51 screen against process order consumption?
Thanks.
Hi
Can you go to SPRO Materials Management-Inventory Management-Reporting-Define field selection for material doc list
You can add the field KOSTL
Regards
Raghavendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
You don't need to bring the cost center in MB51.
The production order settlement rule will have a reference to the cost center and the goods movements will be posted with a reference to a sales orders. Therefore, when running the order settlement, the goods movement cost will be settled to the cost center.
Regards,
Caetano