on 05-15-2018 11:46 AM
Hi All,
Can anyone tell me is it possible in SAP standard to post service entry sheet with reference to network-activity having "CRTD" status or it's status should be "REL".
If it's not possible, kindly share some helpful link i-e help.sap or some other for reference.
Regards,
Faizan
It should always be released; CRTD means it is waiting for approval; there is plenty of documentation on this at help.sap.com using the search
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tammy,
Thanks for your reply.
This is my scenario, I have created project --> WBS --> Network --> Activity which all have "CRTD" status. Now on same status, PR and PO created with reference to Network-Activity and when posting service entry sheet, getting below error.
When I try to release my network, I got below error. I also try to release my top level project but still getting same error.
So can you tell me on project,WBS and network "CRTD' status if PR and PO created, then it can't be set to "REL" status again?
Regards,
Faizan
check user status if they have same business transaction behind configuration so might be the reason behind this block.
such release means approval, and system will allow to execute the business transaction as PR PO MIGO SES and more...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.